Corio Quay Nth wharf is a multi purpose Berth which also provides access for a woodchip ship loader. The current ship loader facility is being replaced as it nears the end of its useful life. The new facility will increase the size of shipping that can berth for the next 20 years. The works required to construct the new facility include;
- Breast & Mooring dolphins
- Ship loading platform
- Ship gangway.
Gertzel Engineering Surveyors was contracted to the McConnell Dowel for the provision of surveying services for the project. Survey works so far have comprised;
- Construction set out
- Services drawing/as-built
- As-built construction details
- Design verification
Project Summary
- Project
- Corio Quay
- Location
- Corio, VIC
- Client
- McConnell Dowel
- Discipline
- Marine
- Date
- 2009